Construction

Metro Water Recovery is routinely working to improve our infrastructure. Here are our ongoing projects:

Platte River Interceptor Rehabilitation Project

As part of ongoing system maintenance, Metro Water Recovery is rehabilitating segments of sanitary sewer pipe in our service area.

The Platte River Interceptor Rehabilitation project is necessary to maintain approximately 4 miles of sewer pipe, mainly located in the City and County of Denver, that were identified as being severely corroded.

The construction method (known as โ€œcured in place pipe or CIPPโ€) allows work to be completed within a relatively small footprint by inserting a liner into the pipe that is cured with heat to become a pipe within a pipe. However, CIPP installation cannot be performed during live flow conditions and requires temporary above-ground bypass pumping. Short-term road closures and/or traffic detours will be required along the route.

Metro is committed to completing this routine maintenance project safely and efficiently with minimal disturbance to local businesses, residents, and visitors.

What to expect during construction:

  • Work will occur from December 2025 through April 2027. Construction is scheduled to minimize disruption to outdoor spaces; schedule is weather dependent and subject to change. Upon completion, worksites will be restored to preconstruction conditions and crews will move to the next location.
  • Brief disturbances will be limited to a series of ten worksites (approximately 4-8 weeks per site). The first bypass setup will likely begin the first or second week of December 2025.

Measures to reduce odor, noise, and traffic impact

  • Odor
    Worksites primarily use existing manholes and require no open pipelines; materials may have an odor similar to modeling glue for brief periods during installation of CIPP lining.
  • Noise
    Bypass pumps must run continuously during installation of CIPP lining; crews will work extended shifts to complete this work as efficiently as possible.
  • Safety
    Active bypass pumping systems will be monitored 24/7 for security.
  • Traffic
    All short-term road and parking closures will adhere to pre-approved City of Denver and/or Colorado Department of Transportation (CDOT) protocols.
illustration of CIPP process
Typical CIPP process

Contact Us

Contact us with questions regarding the Platte River Interceptor Rehabilitation Project

Project Hotline

303-286-3115 (English)
303-286-3116 (Espaรฑol)

Anne Marie Boger

Community Engagement Liaison

720-484-4860

Amy Lovatt

Public Information Officer

720-400-8633

publicinfo@metrowaterrecovery.com

Accessibility questions

accessibility@metrowaterrecovery.com

Platte River Interceptor Rehabilitation Project Anticipated* Work Schedule

*Subject to change

PAR 1461 map with various segments of construction along the South Platte River. Segment 3 is north of W Bayaud Ave. Segment 4 is South of 6th Ave Freeway along the river. Segment 5 stretches north of 6th Avenue to West Colfax. Segment 6 is near Empower field along the river. Segment 7 and Segment 8 is located near Elitch Gardens and The Downtown Aquarium along the South Platte River
PAR 1461 Map showing Segment 2 from Florida Ave through Ruby Hill Park. Segment 9 along W Evans Avenue East of the South Platte River and Segment 1 along the South Platte river south of West Dartmoth Ave